Installation information for ER-UPD housing

(also Requirements in line with approval and approval)

ER-UP/G are equipped with a plastic housing without fire protection equipment. The ER-UP/D housing may be installed in the following installation positions:

They can be installed with an air outlet direction (exhaust socket) upwards, to the right or left and are suitable for ceiling installation. With an upwards air outlet direction, the yoke spring should be removed from the shut-off device.

A description of ceiling installation in a suspended ceiling can be found below. In the case of non-suspended ceilings, the housing is mounted directly on the ceiling.

Wall installation should be undertaken as described for ceiling installation. Suitable mounting material is to be provided by the customer. To screw down the connection duct use steel screws, if screwing into brickwork/concrete use steel dowels.

The metal shut-off device should be prepared according to these instructions.

The ER-UPD housing must be inserted without any distortion. Failure to do so will mean that the fan insert cannot engage correctly in the ER-UPD housing and the degree of protection stated on the rating plate is no longer ensured.

Break open one of the housing segments [S] to use the second room connection set ER-ZR.

Use ER-MO expanded rubber for acoustic insulation of thin ceilings capable of resonance.

A toilet seat air extraction unit is connected to the ER-UPD housing using the DN 70 extraction socket ER-AS.